Skip to main content

WPS Paving Project 7-26-2021 to 8/??/2021

 DAY ONE, July 26, 2021

A special thanks to R&D Paving out of Franklin, NH for their work and expertise for this paving project.  Jeff Twarog and others from this company were great about communicating and answering questions during the entire project.  C&W Services and Dover School District Facilities Director Michael Brooks and Dover School District Business Administrator Michael Limanni were also instrumental in making this project happen during all of its phases. To all of the previously mentioned and the other sub-contractors, thank you from Woodman Park School.

"The Reclaimer"  This machine scrapes the pavement and tills it into the ground material underneath.


This Pad Foot Roller compresses and dimples the base before adding stone.  


The Reclaimer is tilling/grinding in stones to make a more firm base before the pavement is added.


The "Gas Station/Lower Foyer" parking lot is being worked on as well.



DAY TWO, July 27, 2021


Bus Loop by the Tennis Courts


Bus Loop by the Basketball Courts


Parking by Door 5


Reclaimer by Door 5


Pre-School Entrance Parking Lot


Lower Foyer Parking Lot


Gas Station Parking Lot


Cafeteria Parking Lot


Rain Garden Road



DAY THREE, July 28, 2021

The Gas Station Lot gets more base material.


Family Drop Off/Pick Up Loop near the playground gets compacted and leveled.

Family Loop to Bus Loop Intersection gets more material and graded to the proper depth for a solid base.  This project goes all the way from the Bus Loop to Parker Street.

Bus Loop gets material added/removed to reach the proper depth for a base before paving. 


The Grader moving material before compaction by the rollers. 


DAY FOUR, August 2, 2021

Paving equipment dropped off today.


Front view of a paver.

"Dave the Grader" moving material in preparation for the next day's "Binder" base coat.


DAY FIVE, August 3, 2021
The base "Binder" coat is being laid down today.  The Binder coat is more coarse than a top coat and is delivered at around 130-200 degrees in temperature. The Paver was filled and has its sides down in this picture.

Here the Paver has its sides up to help move the material to the back to the Sifter section.

"Joe the Foreman" has a control attached to the Sifter to help determine the depth (thickness) of the base Binder coat of pavement. 

The Paver and Dump Truck move at the same rate of speed so an even coat can be applied. 

Here, Joe is using a level to make sure the slope of the Binder coat is flat and in the correct direction.  The teenager in the black coat is new to the profession and works at least 50-60 hours a week as a summer job.

View from the Pre-School Entrance to the Lower Foyer Entrance.

Family Drop Off to the Bus Loop Intersection.  

Looking down from the Family Drop Off to the lower parking by Door #5.  

Dump Truck and Paver working in unison. 

The truck driver asked that this picture be taken for him.  He is proud of his truck. 


The Roller is getting a lot of use and compacts the very hot Binder Coat down a lot. 


View from the Bus Loop by the Tennis Courts looking toward the Base Ball Field. 

View from the road by the Rain Garden.


DAY SIX, August 4, 2021
The curb is being re-set in the bus loop.

Granite curbing to be reused.

Skid Steer with a scissor pincher/grabber taking out the curbs. 

Setting the edge with the granite curbs. Cement is being added between the curbs in this picture.


DAY SEVEN, August 6, 2021

The Bus Loop Sidewalk was prepped, compacted, and paved. 

The Roller and Tamper have been busy. 

The dump truck and skid steer fill the paver and the rest is done by the workers.


DAY EIGHT, August 9, 2021

The Sidewalk of the Bus Loop is getting a final top coat.

The "Shimming" paving work was completed near the curbs and now a final top coat will be added. 

The angles, depth, placement, and feed rate are all taken into account.  There are at least a handful of workers and they often use non-verbal hand signals to communicate due to the noise. 

There is an auger (hard to see) in the apparatus to move the paving material from the green bin to the spreader.

The dump truck has to go at certain rate of speed while lifting the dump body to fill the paver as they both move forward, 

The roller compacts the top coat.  It also has a sprayer that puts water on the roller wheels to help cool both the machine and the top coat of pavement. The water also prevents pieces of the pavement from sticking to the roller wheels. 

View of the Door #5 Parking Lot and ramp up to the Family Drop Off line. 

Cliff is the driver of the Tack Truck.  "Tack" is an adhesive that goes on the binder (base) coat before the final layer of pavement is placed on top. Tack has to be at the temperature of 167 degrees Fahrenheit before added to the surface of the binder coat.  This truck keeps the tack liquid heated until applied by extended arms or hose. 



DAY TEN, August 10, 2021

The painters from Lakes Region Striping Company are measuring and using chalk to mark where the parking lines need to go. 

The painter is using a line striper to paint the white parking lines.  The process goes very quickly.

Bus Loop view by the tennis courts.

A closer view of the Bus Loop by the tennis courts.

Bus Loop view by the basketball courts. 

A closer view of the Bus Loop by the basketball courts.

Family Drop Off Lot

Door #5 Lot

Pre-School Entrance Lot

Lower Foyer Lot

Gas Station Lot

Cafeteria Lot

Rain Garden Road








Comments

  1. The asphalt is actually delivered at Approx 280-300 degrees. Behind the paver after it passes through the paver it is Approx 250-270 degrees.

    ReplyDelete

Post a Comment

Popular posts from this blog

WPS Staff Northeast Passage Wheelchair Handball Game: March 24, 2022

  WPS Staff Northeast Passage Wheelchair Handball Game March 24, 2022

WPS Hot Water Heater Work 7-26-2021 to 8/?/2021

 July 26, 2021 The main units have been delivered and fit through the doors to the Boiler Room.  The copper piping has been delivered. July 28, 2021 Reworking the piping and other set up.   August 2, 2021 Hot water heater units in place on flood pad. The piping is laid out to ensure all pieces are correct and to the proper code.  For example, the yellow handled shut off valves shown at the bottom of the picture are not the correct ones and will be replaced (good catch by John the installer from NPI). August 3, 2021 Hot Water Heater #1 being assembled.  Notice the small level on the horizontal run that is perpendicular to the wall.   There are a lot of codes to follow in plumbing.  More hardware install that includes Hot Water Heater #2. August 5, 2021 The gas line was added.  It is the black pipe in the middle of the photo that leads to the black control box at the base of Water Heater #1.  A major shut off valve will be added soon and eventually the former gas line will be taken out (