DAY ONE, July 26, 2021 A special thanks to R&D Paving out of Franklin, NH for their work and expertise for this paving project. Jeff Twarog and others from this company were great about communicating and answering questions during the entire project. C&W Services and Dover School District Facilities Director Michael Brooks and Dover School District Business Administrator Michael Limanni were also instrumental in making this project happen during all of its phases. To all of the previously mentioned and the other sub-contractors, thank you from Woodman Park School. "The Reclaimer" This machine scrapes the pavement and tills it into the ground material underneath. This Pad Foot Roller compresses and dimples the base before adding stone. The Reclaimer is tilling/grinding in stones to make a more firm base before the pavement is added. The "Gas Station/Lower Foyer" parking lot is being worked on as well. DAY TWO, July 27, 2021 Bus Loop by the Ten...