July 26, 2021
The main units have been delivered and fit through the doors to the Boiler Room.
The copper piping has been delivered.
July 28, 2021
Reworking the piping and other set up.
August 2, 2021
August 10, 2021
Hot water heater units in place on flood pad.
The piping is laid out to ensure all pieces are correct and to the proper code. For example, the yellow handled shut off valves shown at the bottom of the picture are not the correct ones and will be replaced (good catch by John the installer from NPI).
August 3, 2021
Hot Water Heater #1 being assembled. Notice the small level on the horizontal run that is perpendicular to the wall. There are a lot of codes to follow in plumbing.
More hardware install that includes Hot Water Heater #2.
August 5, 2021
The gas line was added. It is the black pipe in the middle of the photo that leads to the black control box at the base of Water Heater #1. A major shut off valve will be added soon and eventually the former gas line will be taken out (it is in the way of some new piping that is being installed).
August 6, 2021
Hot Water Heater #2 is getting some piping attention.
Shut Off Valve was installed high up on the Boiler Room Ceiling. Not an easy job!
Piping, gauges, and valves added to Hot Water Heater #1
Piping, gauges, and valves added to Hot Water Heater #2
August 13, 2021
Some gauges and relief valves have been added. Gas piping have been added as well.
Core drilling for the gas vents were started. Small mishap with water from the core driller hitting some electrical boxes set off trouble alarms in the alarm panel. A nice visit by Dover Fire followed.
Comments
Post a Comment