WPS Hot Water Heater Work 7-26-2021 to 8/?/2021

 July 26, 2021

The main units have been delivered and fit through the doors to the Boiler Room. 


The copper piping has been delivered.


July 28, 2021

Reworking the piping and other set up.


 
August 2, 2021

Hot water heater units in place on flood pad.



The piping is laid out to ensure all pieces are correct and to the proper code.  For example, the yellow handled shut off valves shown at the bottom of the picture are not the correct ones and will be replaced (good catch by John the installer from NPI).



August 3, 2021

Hot Water Heater #1 being assembled.  Notice the small level on the horizontal run that is perpendicular to the wall.   There are a lot of codes to follow in plumbing. 

More hardware install that includes Hot Water Heater #2.


August 5, 2021

The gas line was added.  It is the black pipe in the middle of the photo that leads to the black control box at the base of Water Heater #1.  A major shut off valve will be added soon and eventually the former gas line will be taken out (it is in the way of some new piping that is being installed). 


August 6, 2021
Hot Water Heater #2 is getting some piping attention. 


Shut Off Valve was installed high up on the Boiler Room Ceiling.  Not an easy job!



August 10, 2021
Piping, gauges, and valves added to Hot Water Heater #1

Piping, gauges, and valves added to Hot Water Heater #2

August 13, 2021

Some gauges and relief valves have been added. Gas piping have been added as well.

Core drilling for the gas vents were started. Small mishap with water from the core driller hitting some electrical boxes set off trouble alarms in the alarm panel.  A nice visit by Dover Fire followed. 







Comments

Popular posts from this blog

WPS Paving Project 7-26-2021 to 8/??/2021

  DAY ONE, July 26, 2021 A special thanks to R&D Paving out of Franklin, NH for their work and expertise for this paving project.  Jeff Twarog and others from this company were great about communicating and answering questions during the entire project.  C&W Services and Dover School District Facilities Director Michael Brooks and Dover School District Business Administrator Michael Limanni were also instrumental in making this project happen during all of its phases. To all of the previously mentioned and the other sub-contractors, thank you from Woodman Park School. "The Reclaimer"  This machine scrapes the pavement and tills it into the ground material underneath. This Pad Foot Roller compresses and dimples the base before adding stone.   The Reclaimer is tilling/grinding in stones to make a more firm base before the pavement is added. The "Gas Station/Lower Foyer" parking lot is being worked on as well. DAY TWO, July 27, 2021 Bus Loop by the Ten...

WPS Staff Northeast Passage Wheelchair Handball Game: March 24, 2022

  WPS Staff Northeast Passage Wheelchair Handball Game March 24, 2022